Removal of Infrastructure & Belt at Underground Conveyor
Client: Boliden Tara Mine DAC, Navan Co. Meath
PSDP: ATC Building Surveying & Engineering Consultancy Ltd
Works Contractor & PSCS: SEM Construction
Removal of 124m conveyor belt and supporting steel infrastructure
Creation of safe working zone & exclusion zone
Manual scaling of back & sidewalls before & after dismantling conveyor infrastructure
Snip & remove conveyor belt using 8t hydraulic metal shears in sizeable chunks
Remove conveyor infrastructure incl, old steel stringer sections & trough rollers
Removal of steel / materials to surface for controlled disposal