Tara Mines Return Air Raise Civil Works, Navan, Co. Meath

Client: Boliden Tara Mine DAC
Architect: Golder Associates Ireland Limited
Works Contractor & PSCS: SEM Construction

  • 300m roadway access to the development site

  • Construction site compound

  • Removal of topsoil and overburden to bedrock level (~ 10m) and stockpiling material including: 10,400m3 subsoil/till material & 160m3 rock

  • Construction of concrete foundation (10m x 10m x 0.5m) on bedrock to mount the raise-bore drilling for 4.5m Diameter shaft

  • Re-use of material for safety berms & settlement pond embankments

  • Formation of swales and sumps to aid the site drainage and final landscape finish.

Timelapse video of Return Air Raise Construction

3D Model of RAR Site Works